Question 8.20: On January 15 of Year 1, a company decides to hedge the purchase of 100,000 bushels of corn on February 15 of Year 2. The following table gives futures prices (cents per bushel) of three selected contracts on four different dates. Explain how the company can use the contracts to create the required hedge. What is the net (after hedging) price paid for the corn as a function of the spot price on February 15 of Year 2? Each corn contract is on 5,000 bushels.

garp-t3-8.20.jpg

Answer:

20200802_012504.jpg
It want to hedge purchase -> afraid price going up -> to hedge, it need long future? Instead of short as in the answer.

Or did I miss anything here?

Thanks!
 
Last edited by a moderator:

enjofaes

Active Member
Question 8.20: On January 15 of Year 1, a company decides to hedge the purchase of 100,000 bushels of corn on February 15 of Year 2. The following table gives futures prices (cents per bushel) of three selected contracts on four different dates. Explain how the company can use the contracts to create the required hedge. What is the net (after hedging) price paid for the corn as a function of the spot price on February 15 of Year 2? Each corn contract is on 5,000 bushels.

View attachment 2847

Answer:

View attachment 2796
It want to hedge purchase -> afraid price going up -> to hedge, it need long future? Instead of short as in the answer.

Or did I miss anything here?

Thanks!
Just a heads up, still not fixed in 2022
 