Dear David,
I am confuse with the following concept and would appreciate if you could clarify.
Shall RAROC or ARAROC be used to determine the viability of a project?
The study note seems to suggest that ARAROC shall be used but the practice question 1.5 as set out below seem to tell otherwise.
Question 1.5 in the practice question under RAROC:
Why is The answer of I which state that "If a prject's RAROC is greater than the firm's cost of equity capital, then the project should be accepted" is consider true? Shouldn't ARAROC be used instead?
Thank you.
I am confuse with the following concept and would appreciate if you could clarify.
Shall RAROC or ARAROC be used to determine the viability of a project?
The study note seems to suggest that ARAROC shall be used but the practice question 1.5 as set out below seem to tell otherwise.
Question 1.5 in the practice question under RAROC:
Why is The answer of I which state that "If a prject's RAROC is greater than the firm's cost of equity capital, then the project should be accepted" is consider true? Shouldn't ARAROC be used instead?
Thank you.